Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the details contained in the planning application forms received by the Local Planning Authority on 14th September 2018.and the revised drawing no. 920/6 A received on 28th November 2018. The reason for the condition is :- For the avoidance of doubt.
3.The flats hereby permitted shall not be occupied until the conversion work has been carried out entirely in accordance with the approved drawing no. 920/6 A including the replacement of the Matthes sign and balustrade. The reason for the condition is:- In order to ensure a satisfactory standard of accommodation and in the interests of the visual appearance of the area.
4.Demolition and construction work shall not take place outside the following hours:- 08:00 to 18:00 Monday to Friday 08:30 to 13:30 Saturday and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
5.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the aims of Policies CS1 & CS11 of the Great Yarmouth Local Plan: Core Strategy and saved Policy HOU7 of the Great Yarmouth Borough-Wide Local Plan.
6.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. It is confirmed that this shadow HRA submitted by the applicant has been assessed as being suitable for the Borough Council as competent authority to use as the HRA record for the determination of the planning application, in accordance with the Conservation of Habitats and Species Regulations 2017.
7.NOTES - Please read the following notes carefully:- The Environmental Health Officer has made the following comments which should be taken into account before and during the course of construction:- a) Noise pollution from development: The work has the potential to cause a noise nuisance to local residents living nearby the development phase. The applicant should undertake an informal noise assessment of this aspect. This should address issues surrounding, for example, choice of plant, hours of work and deliveries of materials. b) Asbestos removal: The developer must carry out an asbestos survey prior to construction of the building if it likely that potential asbestos materials could be disturbed. The purpose of the survey would be to identify asbestos containing materials (ACMs). The developer has a legal duty to remove most ACMs before demolition/ construction and some ACMs must be removed by contractors licensed by the Health and Safety Executive (HSE). If at any stage during demolition asbestos is suspected the work should be stopped and the material investigated. c) Local Air Quality: The site will potentially generate dust during the construction process; therefore, the following measures should be employed:- · An adequate supply of water shall be available for suppressing dust; · Mechanical cutting equipment with integral dust suppression should be used; · There shall be no burning of any materials on site. · Where there is potential for significant dust generation then the developer should consider the use of screening around the site.