| No. | Condition Text |
|---|
| 1. | This permission expires on 20th November 2020 and unless on or before this date application has been made for an extension to the period of permission and such application is approved by the Local Planning Authority the use shall be discontinued.
The reason for the condition is :-
In order to retain control over the use of the site to ensure the town wall is not adversely affected by the development. |
| 2. | No use of the development hereby permitted shall occur outside of the following hours: 08:00 - 17:00 Monday to Friday 08:30 - 13:30 Saturday No works shall take place on Sundays or Bank Holidays.
The reason for the condition is :-
In the interests of the amenities of local residents. |
| 3. | Outside of the existing buildings on site no materials shall be stored and no activities undertaken within 1.5 metres of the town wall for the first 20 metres into the site as measures from the edge of the highway carriageway (South Quay) and no materials shall be stored and no activities shall be undertaken within 3 metres of the town wall for the remainder of the site.
These prescribed distances shall be demarcated by a protective barrier. The details of the protective barrier shall be submitted to and approved by the Local Planning Authority within 4 weeks from the date of this permission. The barrier shall be erected in accordance with the approved details and shall remain in situ whilst the use of the salvage yard continues.
The reason for the condition is :-
In the interests of protecting the wall from damage and providing adequate access. |
| 4. | Within the existing workshop no material shall be stored and no activities undertaken within 1 metre of the town wall.
The reason for the condition is :-
In the interests of protecting the wall from damage. |
| 5. | No materials or equipment shall be stored within the site at a height greater than 4 metres at any time.
The reason for the condition is :-
In the interests of protecting the visual amenity of the town wall. |
| 6. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria as outlined in policies CS06 and CS10 of the Core Strategy |
| 7. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |