| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the revised plans (drawing reference: HS/17/QS/109 Rev A, HS/17/QS/110 Rev A, HS/17/QS/111 Rev A and HS/17/QS/112 Rev A) and addition detail received by the Local Planning Authority on 23 August 2018.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | A Minimum vertical clearance of 2.1 metres shall be maintained at all times between the base of proposed structure (lighting units) and the level of the adjacent public highway and shall not project more than 0.5 metres from the principal elevation of the building they are attached to.
The reason for the condition is :-
In the interests of highway safety. |
| 4. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria outlined in policies CS9 and CS10 of the adopted Core Strategy. |
| 5. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |
| 6. | NOTES - Please read the following notes carefully:-
Please note that this permission does not provide advertisement consent. Should you wish to install any advertisements that require planning permission then a separate advertisement consent is required. |