| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the details contained in the planning application forms and drawing no's. 0000/2018/PL100, 0000/2018/PL211 Rev. A and 0000/2018/PL112 received by the Local Planning Authority on 19th March 2018 and the revised drawings 0000/2018/PL121 Rev. C, 0000/2018/PL124 Rev. C, 0000/2018/PL125 Rev. C, J32-3471-PS-001 and J32-3471-PS-003 received on 24th April 2018.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | Prior to the commencement of the use hereby permitted, a 2.4 metre wide parallel visibility splay (as measured back from the near edge of the adjacent highway carriageway) shall be provided across the whole of the site's roadside frontage. The parallel visibility splay shall thereafter be maintained at all times free from any obstruction exceeding 0.6 metres above the level of the adjacent highway carriageway.
The reason for the condition is :-
In the interests of highway safety. |
| 4. | Prior to the commencement of the use hereby permitted, the proposed access, on-site car and cycle parking, servicing, turning and waiting areas shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use.
The reason for the condition is :-
To ensure the permanent availability of the parking/manoeuvring area, in the interests of highway safety. |
| 5. | Prior to the commencement of the development a monitoring programme to assess the level of on-street parking on Jones (GC) Way resulting from the development shall be submitted to and approved in writing by the Local Planning Authority in consultation with Norfolk County Council as the local highway authority. The monitoring programme shall be implemented as agreed unless the Local Planning Authority gives written approval to any variation.
The reason for the condition is :-
To ensure that agreed traffic/parking levels are not breached and the highway network is adequate to cater for the development proposed. |
| 6. | Subject to the findings of the monitoring programme referred to in condition 5 of this permission, if required by the Local Planning Authority in discussion with the Highway Authority, the applicant shall fund the promotion of appropriate Traffic Regulation Order(s) for parking/loading restriction.
The reason for the condition is :-
In the interests of highway safety. |
| 7. | In the event that contamination that was not previously identified is found at any time when carrying out the approved development, it must be reported in writing immediately to the Local Planning Authority. All development shall cease and shall not recommence until:
a) A report has been submitted and agreed in writing by the Local Planning Authority which includes results of an investigation and risk assessment together with proposed remediation scheme to deal with the risk identified; and
b) The agreed remediation scheme has been carried out and a validation report demonstrating its effectiveness has been approved in writing by the Local Planning Authority.
The reason for the condition is :-
To establish whether the land is contaminated and to secure any measures necessary to protect the future users of the site. |
| 8. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the aims of Policies CS6 and CS7 of the Great Yarmouth Local Plan: Core Strategy. |
| 9. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner. |
| 10. | NOTES - Please read the following notes carefully:-
a) This planning permission is linked to a Section 106 Agreement dated ????
b) It is an OFFENCE to carry out any works within the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. This development involves work to the public highway that can only be undertaken within the scope of a Legal Agreement between the applicant and the County Council. Please note that it is the applicant's responsibility to ensure that, in addition to planning permission, any necessary Agreements under the Highways Act 1980 are also obtained. Advice on this matter can be obtained from the County Council's Highways Development Management Group based at County Hall in Norwich, tel. 0344 800 8020.
Public Utility apparatus may be affected by this proposal. Contact the appropriate utility service to reach agreement on any necessary alterations, which have to be carried out at the expense of the developer.
If required, street furniture will need to be repositioned at the applicant's expense.
c) The applicant's attention is drawn to the attached advice from Norfolk Constabulary regarding security for the development. |