| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | Within 1 month of the date of this planning permission the wattle screen, of a minimum height of 1.8m and minimum width of 1.5m, as shown on the submitted plan (dated 3rd of July 2018) shall be erected and retained in the approved form thereafter. Unless otherwise agreed in writing by the local planning authority this screen shall not allow views through.
The reason for the condition is:-
In the interests of the visual amenities of the locality |
| 3. | The development shall be carried out in accordance with the plans received by the Local Planning Authority on 3rd of July 2018.
The reason for the condition is :-
For the avoidance of doubt. |
| 4. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria for domestic additions set out in saved Policy HOU18 of the Great Yarmouth Borough-Wide Local Plan. |
| 5. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |