1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the plan (drawing reference: 17-2497-1 and 17-2497-3) received by the Local Planning Authority on 8 February 2018 and the revised plan (drawing reference: 17-2497-4A) received by the Local Planning Authority on 7 June 2018 and the revised plan (drawing reference: 17-2497-2 Rev B) received by the Local Planning Authority on 15 June 2018. The reason for the condition is :- For the avoidance of doubt.
3.Construction work shall not take place outside the following hours:- 07:30 to 18:00 Monday to Friday 08:00 to 13:00 Saturday and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
4.Prior to the first occupation of any residential unit hereby approved details of a bin store to be incorporated into the amenity space as shown on the approved plans shall be submitted to and approved in writing by the Local Planning Authority. The bin store shall remain available for that use thereafter. The reason for the condition is :- To ensure the adequate storage of bins for the purposes of visual amenity.
5.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria outlined in saved policy HOU7 of the Borough Wide Local Plan and policies CS2, CS3 and CS9 of the adopted Core Strategy.
6.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF.
7.NOTES - Please read the following notes carefully:- Please read Environmental Health comments dated the 27 February 2018.