| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the application form and approved plans (drawing reference: BP2-SSLOC 01and GTC-E-SS-0012_R1-8_1_of_1) received by the Local Planning Authority on19 December 2017.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | Prior to commencement of the development hereby approved a BS4142 survey shall be undertaken which will detail the noise levels of the approved substation and full mitigations measures. The BS4142 survey shall be submitted to and approved by the Local Planning Authority in consultation with the Head of Environmental Services.
The development shall be carried out in accordance with the approved details and all approve mitigation measures shall be completed prior to the first use of the substation.
The reason for the condition is :-
In the interests of neighbouring amenities and ensuring suitable noise levels. |
| 4. | Construction work shall not take place outside the following hours:-
07:30 to 18:00 Monday to Friday
08:00 to 13:00 Saturday
and no work shall take place on Sundays or Bank Holidays.
(These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property)
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 5. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria outlined in policy CS9 of the adopted Core Strategy. |
| 6. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |
| 7. | NOTES - Please read the following notes carefully:-
The access to the site is across a public right of way. The public right of way must remain open and un-obstructed for the duration of the development. |