1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the revised plan (DWG. 588 03/5 REV A) received by the Local Planning Authority on 20.12.2017 and plans (DWG. 588 03/01, 588 03/03, 588 03/02, 588 03/04, 588 06/03) received by the Local Planning Authority on 07.11.2017. The reason for the condition is :- For the avoidance of doubt.
3.Notwithstanding the roof materials set out in the application form the roof of the proposed extension should be completed in Dark (lead) grey single ply membrane (manufactured by Sarnafill) unless otherwise agreed in writing by the Local Planning Authority. The reason for the condition is :- In the interests of visual amenity
4.Prior to the commencement of use, a flood response plan shall be submitted to and agreed in writing with the Local Planning Authority. This flood response plan, including information regarding the availability of the Environment Agency's Flood Warnings Service, shall be made available to managers/staff and visitors of the site. The reason for the condition is :- To minimise the risk to the visitors and staff in the event of flooding.
5.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria as set out in policy CS10 Safeguarding local heritage assets and Policy CS8: Promoting tourism, leisure and culture
6.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF.
7.NOTES - Please read the following notes carefully:- BPA do not have any objection, in principle to the proposals, but wish to ensure that any works in the vicinity of this major accident hazard high pressure gas pipeline does not affect the overall integrity, and that they are carried out in accordance with our safety requirements. The most important points to consider are as follows: 1) These are Major Hazard Pipelines 2) Any construction must be kept to a minimum of 6m from the pipeline 3) All excavations (including hand trail holes) within 6m of the pipeline must be approved and supervised by BPA. 4) The exact location of the pipeline to be marked by BPA in consultation with the developer prior to detailed design. 5) Nominal cover is only 0.9m (3'). 6) Normal vertical clearance for new services is 600mm. 7) These Pipelines are protected by cathodic protection and you should consult the BPA if you are laying HV cables or ferrous services (with or without cathodic protection). 8) Heavy vehicular crossing points to be approved before use across the easement. 9) Tree planting is prohibited within the 6m easement. 10) No lowering or significantly raising of ground level throughout the easement. 11) Roadways should, where possible, cross the pipelines using the appropriate protection detailed in Appendix 1 of the enclosed booklet and not run along the pipeline route. 12) A Continuous site presence will be required whilst the pipeline/s are exposed. To obtain more detail of the pipeline's location, please contact Adam Canning on 01442 218846 and quote the BPA reference.