1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the revised plan (dwg.no. RM revision A) received by the Local Planning Authority on 27th February 2018. The reason for the condition is :- For the avoidance of doubt.
3.No work shall commence until details of the exact type and colour of the facing bricks and roof tiles have been submitted to and approved by the Local Planning Authority. The building(s) shall thereafter be constructed using the agreed materials. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of these materials have not been submitted.
4.Prior to the commencement of the development and to the satisfaction of the Environmental Services Manager, a Phase 1 contamination report shall be carried out to assess whether the land is likely to be contaminated. The report shall also include details of known previous uses and possible contamination arising from those uses. If contamination is suspected to exist, a Phase 2 site investigation is to be carried out to the satisfaction of the Environmental Services Manager. If the Phase 2 site investigation determines that the ground contains contaminants at unacceptable levels then the applicant is to submit a written strategy detailing how the site is to be remediated to a standard suitable for its proposed end-use to the Environmental Services Manager. No buildings hereby permitted shall be occupied until the remediation works agreed within the scheme have been carried out to the satisfaction of the Local Planning Authority. The reason for the condition is :- To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
5.In the event that contamination that was not previously identified is found at any time when carrying out the approved development, it must be reported in writing immediately to the Local Planning Authority. All development shall cease and shall not recommence until: 1) a report has been submitted and agreed in writing by the Local Planning Authority which includes results of an investigation and risk assessment together with proposed remediation scheme to deal with the risk identified and 2) the agreed remediation scheme has been carried out and a validation report demonstrating its effectiveness has been approved in writing by the Local Planning Authority. The reason for the condition is :- To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors.
6.No development shall take place until there has been submitted to and approved by the Local Planning Authority a scheme of landscaping, which shall include indications of all existing trees and hedgerows on the land, and details of any to be retained, together with measures for their protection in the course of development. The scheme shall also include details of all boundary treatments. The reason for the condition is:- In the interests of the visual amenities of the locality.
7.Construction work shall not take place outside the following hours:- 07:30 to 18:00 Monday to Friday 08:30 to 13:30 Saturday and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
8.Vehicular and pedestrian access to and egress from the adjoining highway shall be limited to the access(es) shown on approved plans. Any other access(es) or egresses shall be permanently closed, concurrently with the bringing into use of the new access. The reason for the condition is :- In the interests of highway safety.
9.Prior to the commencement of the use hereby permitted the vehicular access to the services road shall be widened to a minimum width of 3m to facilitate vehicular access to the development in accordance with the Norfolk County Council residential access construction specification. Arrangement shall be made for surface water drainage from the site to be intercepted and disposed of separately so that it does not discharge into the highway carriageway. The reason for the condition is :- In the interest of highway safety and traffic movement.
10.Notwithstanding the provisions of Class A of Schedule 2, Part 2 of the Town and Country Planning (General Permitted Development) (England) Order 2015, (or any Order revoking, amending or re-enacting that Order) no gates, bollard, chain or other means of obstruction shall be erected across the approved access unless details have first been submitted to and approved by the Local Planning Authority. The reason for the condition is :- In the interests of highway safety.
11.Prior to the first occupation of the development hereby permitted a 1.0 metre wide parallel visibility splay shall be provided along the north eastern flank frontage (the boundary adjacent to U6V79 Fisher Avenue Back Lane) of the development. The parallel visibility splay shall thereafter be maintained at all times free from any obstruction exceeding 0.6 metres above the level of the adjacent highway carriageway. The reason for the condition is :- In the interests of highway safety.
12.Prior to the first occupation of the development hereby permitted the proposed access and on-site car parking area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use. The reason for the condition is :- To ensure the permanent availability of the parking/manoeuvring area, in the interests of highway safety.
13.NOTES - Please read the following notes carefully:- It is the applicants responsibility to clarify the boundary with the public highway. Private structures such as fences or walls will not be permitted on highway land. The highway boundary may not match the applicants title plan. Please contact the highway research team at highway.boundary@norfolk.gov.uk for further details.
14.This proposal involves excavations adjacent to the public highway. It is an OFFENCE to carry out any works that may affect the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. Please note that it is the applicant's responsibility to ensure that, in addition to planning permission, any necessary consents or approvals under the Highways Act 1980 and the New Roads and Street Works Act 1991 are also obtained from the County Council. Please contact (insert appropriate contact details).
15.This development involves works within the public highway that can only be carried out by Norfolk County Council as Highway Authority unless otherwise agreed in writing. It is an OFFENCE to carry out any works within the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. Please note that it is the applicant's responsibility to ensure that, in addition to planning permission, any necessary consents or approvals under the Highways Act 1980 and the New Roads and Street Works Act 1991 are also obtained from the County Council. Advice on this matter can be obtained from the County Council's Highway Development Management and Operations team on 0344 800 8020. If required, street furniture will need to be repositioned at the applicant's expense. Public Utility apparatus may be affected by this proposal. Contact the appropriate utility service to reach agreement on any necessary alterations, which have to be carried out at the expense of the developer.
16.REASON FOR APPROVAL OF THE APPLICATION :- The proposals meet the criteria for new housing development set out in saved Policy HOU7 of the Great Yarmouth Borough-Wide Local Plan.
17.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF.