| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the details contained in the planning application forms and drawing no. CAL-TOL_DR_100 received by the Local Planning Authority on 21st September 2017 and the revised drawings no's. CAL-TOL_DR_050 and CAL-TOL_DR_200 received on 30th October 2017.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | No work shall commence until the exact type and colour of the facing bricks and roof tiles have been submitted to and approved by the Local Planning Authority.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of these materials have not been submitted. |
| 4. | Prior to the commencement of the development, a flood response plan shall be submitted to and agreed in writing with the Local Planning Authority. This flood response plan, including information regarding the availability of the Environment Agency's Flood Warnings Service, shall be made available to future occupiers of the site.
The reason for the condition is :-
In accordance with the recommendations of the flood risk assessment, to minimise the risk to the occupants in the event of flooding. |
| 5. | No work shall commence until a drawing showing the provision of bin storage areas has been submitted to and approved by the Local Planning Authority. The bin storage areas shall be provided in accordance with the approved drawing prior to the first occupation of the dwellings hereby permitted.
The reason for the condition is :-
In the interests of the visual amenities of the area. |
| 6. | Prior to the first occupation of the dwellings hereby permitted the proposed on-site car parking and turning area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan. The parking area shall thereafter be retained and kept available for that specific use.
The reason for the condition is :-
To ensure the permanent availability of the parking area, in the interests of highway safety. |
| 7. | The development hereby permitted shall be carried out incorporating the measures to mitigate the risk from flooding set out in section 6.3 of the Flood Risk Assessment submitted with the application (Ref: 1786/RE/03-17/01).
The reason for the condition is :-
To ensure that mitigation measures are undertaken as the property is located within an area at risk of flooding. |
| 8. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking and re-enacting the order) no windows or other openings (except those shown on the approved drawings) shall be inserted into the walls or roofs of the dwellings hereby permitted without the prior consent of the Local Planning Authority.
The reason for the condition is:-
In the interests of the residential amenities of the occupiers of adjoining dwellings. |
| 9. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any Order revoking and re-enacting that Order) no dormer windows or other openings to the roof space of the dwellings hereby permitted shall be provided without the prior consent of the Local Planning Authority.
The reason for the condition is:-
In the interests of the residential amenities of the occupiers of adjoining dwellings. |
| 10. | No piling shall take place without the prior approval of the Local Planning Authority as to the method to be used.
If agreed, piling shall be carried out in accordance with the approved details and no piling shall take place outside the following hours:-
09:00 to 17:00 Monday to Friday
09:00 to 13:00 Saturday
and no piling shall take place on Sundays or Bank Holidays.
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 11. | Demolition and construction work shall not take place outside the following hours:-
08:00 to 18:00 Monday to Friday
08:00 to 13:00 Saturday
and no work shall take place on Sundays or Bank Holidays.
(These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property)
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 12. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new housing development set out in Policies CS1 and CS2 of the Great Yarmouth Local Plan: Core Strategy and saved Policy HOU7 of the adopted Great Yarmouth Borough-wide Local Plan |
| 13. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |