| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development hereby permitted shall be carried out strictly in accordance with the details shown on the application forms and approved plans (drawing reference: 601:1A) received by the Local Planning Authority 13th June 2017.
The reason for the condition is:-
For the avoidance of doubt and to ensure the development is carried out in accordance with the correct documentation. |
| 3. | No development shall take place until the following information has been submitted to and approved in writing by the
Local Planning Authority:
(i) a full site survey showing:
the datum used to calibrate the site levels
levels along all site boundaries
levels across the site at regular intervals
floor levels of adjoining buildings
(ii) full details of the proposed finished floor levels of all buildings and hard surfaces.
The development shall be carried out only in accordance with the approved details.
No development shall take place until full details of the finished levels, above ordnance datum, of the ground floors of the proposed buildings, in relation to existing ground levels have been submitted to and approved by the Local Planning Authority. The development shall be carried out in strict accordance with the levels approved.
The reason for the condtions is:-
To ensure that the development takes place in the manner contemplated by the Local Planning Authority and to retain control over any significant changes in levels within the site. |
| 4. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking and re-enacting the order) no extensions shall be built or windows inserted into the walls or roof of the building hereby permitted without the prior consent of the Local Planning Authority.
The reason for the condition is:-
In the interests of the residential amenities of the occupiers of the adjacent property. |
| 5. | Prior to the first occupation of the development hereby permitted the proposed access and on-sitecar parking shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use.
The reason for the condition is:-
To ensure the permanent availability of parking in the interests of satisfactory development. |
| 6. | No work shall commence until the exact type and colour of the facing bricks and roof tiles have been submitted to and approved by the Local Planning Authority.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of these materials have not been submitted. |
| 7. | Construction work shall not take place outside the following hours:-
08:00 to 18:00 Monday to Friday
09:00 to 13:00 Saturday
and no work shall take place on Sundays or Bank Holidays.
(These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property)
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 8. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new housing development set out in saved policy HOU7 of the adopted Great Yarmouth Borough-wide Local Plan and policies CS and CS3 of the adopted Core Strategy. |
| 9. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |