1.No development whatsoever shall take place until full details of the access, appearance, layout, landscaping and scale of the development (herein after referred to as the reserved matters) have been submitted to and approved by the Local Planning Authority and the development shall be carried out strictly in accordance with such approved details. The reason for the condition is:- Such details have not been submitted as part of this application.
2.Application for approval of reserved matters must be made not later than the expiration of three years beginning with the date of this permission and the development must be begun not later than the expiration of two years from the final approval of the reserved matters or, in the case of approval on different dates, the final approval of the last such matter to be approved. The reason for this condition:- The time limit condition is imposed in order to comply with the requirements of Section 92 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
3.This grant of planning permission is for a maximum 5 dwellings only and the most westerly plot shall be single storey only. The reason for the condition is :- In the interestst of avoiding overdevelopment of the site and to avoid significantly and adversely affecting the neighbouring properties.
4.Prior to the commencement of the development and to the satisfaction of the Local Planning Authority in consultation with the Environmental Services Group Manager, a phase 1 contamination report shall be carried out to assess whether the land is likely to be contaminated. The report shall also include details of known previous uses and possible contamination arising from those uses. The reason for the condition is :- The site that is the subject of this application may contain contaminants in view of its existing and previous uses.
5.If contamination is suspected to exist, a Phase 2 site investigation is to be carried out to the satisfaction of the Local Planning Authority in consultation with the Environmental Services Group Manager. If the Phase 2 site investigation determines that the ground contains contaminants at unacceptable levels then the applicant is to submit a written strategy detailing how the site is to be remediated to a standard suitable for its proposed end-use to the Local Planning Authority in consultation with the Environmental Services Group Manager. If remediation works are considered necessary then no dwellings/buildings hereby permitted shall be occupied until the remediation works agreed within the remediation strategy have been carried out to the satisfaction of the Local Authority. The reason for the condition is :- The site that is the subject of this application may contain contaminants in view of its existing and previous uses.
6.Prior to the first occupation of the development hereby permitted the vehicular access shall be provided and thereafter retained at the position shown on the approved plan in accordance with the attached highway specification (Drawing No. TRAD 1). Arrangement shall be made for surface water drainage to be intercepted and disposed of separately so that it does not discharge from or onto the highway carriageway. The reason for the condition is :- To ensure satisfactory access into the site and avoid carriage of extraneous material or surface water from or onto the highway.
7.Notwithstanding the provisions of Class A of Schedule 2, Part 2 of the Town and Country Planning (General Permitted Development) (England) Order 2015, (or any Order revoking, amending or re-enacting that Order) no gates, bollard, chain or other means of obstruction shall be erected across the approved access unless details have first been submitted to and approved by the Local Planning Authority. The reason for the condition is :- In the interests of highway safety.
8.Prior to the first occupation of the development hereby permitted the proposed access and on-site car and cycle area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use. The reason for the condition is :- To ensure the permanent availability of the parking/manoeuvring area, in the interests of highway safety.
9.Notwithstanding the details indicated on the submitted drawings no works shall commence on site unless otherwise agreed in writing until a detailed scheme for the off-site highway improvement works (footway fronting the site and vehcile access) as indicated on Drawing number 34.007B have been submitted to and approved in writing by the Local Planning Authority in consultation with the Highway Authority. The reason for the condition is :- To ensure that the highway improvement works are designed to an appropriate standard in the interest of highway safety and to protect the environment of the local highway corridor.
10.Prior to the first occupation of the development hereby permitted the off-site highway improvement works referred to in condition 9 shall be completed to the written satisfaction of the Local Planning Authority in consultation with the Highway Authority. The reason for the condition is :- To ensure that the highway network is adequate to cater for the development proposed.
11.Construction work shall not take place outside the following hours:- 07:30 to 18:00 Monday to Friday 08:00 to 13:30 Saturday and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
12.Development shall not commence until a scheme detailing provision for on site parking for construction workers for the duration of the construction period has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented throughout the construction period. The reason for the condition is :- To ensure adequate off street parking during construction in the interests of highway safety.
13.No development shall take place until the following information has been submitted to and approved in writing by the Local Planning Authority: (i) a full site survey showing: the datum used to calibrate the site levels levels along all site boundaries levels across the site at regular intervals floor levels of adjoining buildings (ii) full details of the proposed finished floor levels of all buildings and hard surfaces. The development shall be carried out only in accordance with the approved details. No development shall take place until full details of the finished levels, above ordnance datum, of the ground floor(s) of the proposed building(s), in relation to existing ground levels have been submitted to and approved by the Local Planning Authority. The development shall be carried out in strict accordance with the levels approved. The reason for the condtions is:- To ensure that the development takes place in the manner contemplated by the Local Planning Authority and to retain control over any significant changes in levels within the site.
14.No development shall commence until full details of the proposed boundary treatments including height, form and materials have been submitted to and approved in writing by the Local Planning Authority. The development shall be carried out in accordance with the approved details prior to the occupation of each dwelling. The reason for the condition is :- In the interests of visual amenity.
15.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria outlined in saved polciies HOU07, HOU17 and TR4 of the Borough Wide Local Plan and policies CS2, CS3, CS8 and CS9 of the adopted Core Strategy.
16.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF.