| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | No works shall commence on the site until such time as detailed plans of the roads, footways, cycleways, foul and surface water drainage have been submitted to and approved in writing by the Local Planning Authority in consultation with the Highway Authority. All construction works shall be carried out in accordance with the approved plans.
The reason for the condition is :-
To ensure satisfactory development of the site and a satisfactory standard of highway design and construction. |
| 3. | No works shall be carried out on roads, footways, cycleways, foul and surface water sewers otherwise than in accordance with the specifications of the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
To ensure satisfactory development of the site and to ensure estate roads are constructed to a standard suitable for adoption as public highway. |
| 4. | Before any dwelling to be accessed off the proposed estate road is first occupied, the road(s), footway(s) and cycleway(s) shall be constructed to binder course surfacing level from the dwelling to the adjoining County road in accordance with the details to be approved in writing by the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
To ensure satisfactory development of the site. |
| 5. | Prior to the commencement of any works on site a Construction Traffic Management Plan, to incorporate details of on-site parking for construction workers, access arrangements for delivery vehicles and temporary wheel washing facilities for the duration of the construction period shall be submitted to and approved in writing with the Local Planning Authority in consultation with Norfolk County Council Highway Authority. The wheel washing facilities shall be used by all construction traffic exiting the site.
The reason for the condition is :-
In the interests of maintaining highway efficiency and safety. |
| 6. | For the duration of the construction period all traffic associated with the construction of the development will comply with the Construction Traffic Management Plan and unless otherwise approved in writing by the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
In the interests of maintaining highway efficiency and safety. |
| 7. | Notwithstanding the details indicated on the submitted drawings no works shall commence on site unless otherwise agreed in writing until a detailed scheme for proposed roundabout, as indicated in drawing 1663-GA03-172-1, has been submitted to and approved in writing by the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
To ensure that the highway improvement works are designed to an appropriate standard in the interest of highway safety and to protect the environment of the local highway corridor. |
| 8. | The highway improvement works referred to at condition 7 of this permission shall be completed to the written satisfaction of the Local Planning Authority in consultation with the Highway Authority prior to the first occupation of any dwellings served from the proposed estate road.
The reason for the condition is :-
To ensure that the highway network is adequate to cater for the development proposed. |
| 9. | The development shall be carried out in accordance with the plans, forms and additional information received by the Local Planning Authority on the 22nd December 2016.
The reason for the condition is :-
For the avoidance of doubt. |
| 10. | NOTES - Please read the following notes carefully:-
It is an OFFENCE to carry out any works within the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. This development involves work to the public highway that can only be undertaken within the scope of a Legal Agreement between the applicant and the County Council. Please note that it is the applicant's responsibility to ensure that, in addition to planning permission, any necessary Agreements under the Highways Act 1980 are also obtained. Advice on this matter can be obtained from the County Council's Highways Development Management Group based at County Hall in Norwich.
Public Utility apparatus may be affected by this proposal. Contact the appropriate utility service to reach agreement on any necessary alterations, which have to be carried out at the expense of the developer.
If required, street furniture will need to be repositioned at the applicant's expense. |
| 11. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |
| 12. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria for infrastructure improvements set out in Policy CS14 of the Great Yarmouth Core Strategy. |