| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the original groundfloor plan received on the 25th November 2016 and the revised first and second floor plan received by the Local Planning Authority on 4th January 2017.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | Construction or other works shall not take place outside of the hours hereby specified unless the prior writen consent is granted by the Local Planning Authority:
MONDAY TO FRIDAY 8:00am to 6:00pm
SATURDAY 8:00am to 1:00pm
SUNDAY AND BANK HOLIDAYS No work allowed
The reason for the condition is :-
To protect the amentity of the neighbouring residents during the construction phase. |
| 4. | No dwelling shall be occupied until the bin store area for all associated refuse and recycling bins for the approved properties has been set out within the yard indicated on the plan. Thereafter the area would remain in use as the bin store area, no bins shall be stored outside the property or within the front curtilage apart from on allocated collection days.
The reason for the condition is:-
To ensure that the development is satisfactorily completed and to ensure adequate bin storage. |
| 5. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria as set out in saved policy HOU7 of Great Yarmouth Borough-Wide Plan. |
| 6. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |