No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the application form and approved plans (drawing number: CG-INNA-STD-LH Rev D, CG-INNA-AG-RH-ELEV, Drawing OM3LN/04A Rev A and the location plan) received by the Local Planning Authority on 07 October 2016. The reason for the condition is :- For the avoidance of doubt.
3.Notwithstanding the approved plans this permission is for the biomass boiler, the plant room and associated landscaping only and does not provide consent for any other alterations, uses or developments shown on the approved plan. The reason for the condition is :- In the interests of clarity.
4.No development shall take place until there has been submitted to and approved by the Local Planning Authority a scheme of landscaping, which shall include indications of all existing trees and hedgerows on the land, and details of any to be retained, together with measures for their protection in the course of development. The reason for the condition is:- In the interests of the visual amenities of the locality.
5.All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever, is the sooner, and any trees or plants which within a period of 5 years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written consent to any variation. The reason for the condition is:- In the interests of the visual amenities of the locality.
6.Notwithstanding the submitted plans and prior to the commencement of the development hereby approved full details of the chimney and flue shall be submitted to and approved by the Local Planning Authority. The development shall be carried out in accordance with the approved details. The reason for the condition is :- To ensure adequate dispursal of potential pollution and with clean air legislation.
7.Prior to the biomass boiler being brought into use a Noise Assessment shall be submitted to and approved in writing by the Local Planning Authority in consultation with the Environmental Health Department. The Noise Assessment should provide details of the noise emitted by the biomass unit and the noise levels reaching the nearest properties as well as any mitigation measures used to reduce noise levels. The boiler shall be finished and maintained in accordance with the approved details and shall remain as such in perpetuity. The reason for the condition is :- To ensure the noise emitted is acceptable in terms of neighbouring amenity.
8.The plant room hereby approved shall be used to house a biomass unit and shall not be used for any other purpose. The reason for the condition is :- To ensure the unit is not used for any other purpose deemed unaceptable in this location.
9.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria outlined in policy CS9, CS10 and CS12 of the adopted Core Strategy.
10.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF.