| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the application form and flood response plan received by the Local Planning Authority on 11 March 2016, the approved plans (drawing reference: 1296.103 rev A, 1296.109 rev A, 1296.108 rev A and 1296.107 rev A) received by the Local Planning Authority on 25 April 2016 and the Flood Risk Assessment received by the Local Planning Authority on the 18 May 2016.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | Prior to occupation of the units hereby approved a scheme providing full details of noise mitigation and insulation methods including the use of improved glazing shall be submitted to and approved by the Local Planning Authority. The development shall be carried out in accordance with the approved details.
The reason for the condition is :-
In the interests of the amenities of the residents of the new flats. |
| 4. | Construction work shall not take place outside the following hours:-
07:30 to 18:00 Monday to Friday
08:30 to 13:30 Saturday
and no work shall take place on Sundays or Bank Holidays.
(These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property)
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of nearby dwellings. |
| 5. | Prior to occupation of the units hereby approved the new bin store shown on the approved plans shall be completed and the bins shall be stored therein perpetuity.
The reason for the condition is :-
In the interests of visual amenity. |
| 6. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria outlined in saved policy HOU07 of the Borough Wide Local Plan and policies CS2, CS3 and CS6 of the adopted Core Strategy. |
| 7. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |
| 8. | NOTES - Please read the following notes carefully:-
Please read the environmental health memorandum carefully and ensure that the fire safety, ventilation and local air quality comments are utilised during the development. |