1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the application form received by the Local Planning Authority on the 17 February 2016 and the certificate B received on the 15 June 2017 and approved plans (drawing reference: 1508.15.3 and 1508.15.4) received by the Local Planning Authority on the 17 February 2016 and the revised plan (drawing reference: 1508.12.2D) received by the Local Planning Authority on 25 April 2016. The reason for the condition is :- For the avoidance of doubt.
3.Vehicular and pedestrian (and cyclist) access to and egress from the adjoining highway shall be limited to the access(es) shown on drawing No. 1508.12.2D only. Any other access(es) or egresses shall be permanently closed, and the footway / highway verge shall be reinstated in accordance with a detailed scheme to be agreed with the Local Planning Authority in consultation with the Highway Authority, concurrently with the bringing into use of the new access. The reason for the condition is :- In the interests of highway safety.
4.No part of the proposed structure (to include fascia board / rainwater goods and guttering) shall overhang or encroach upon highway land and no gate / door / ground floor window if installed shall open outwards over the highway. The reason for the condition is :- In the interests of highway safety.
5.Prior to the first occupation of the development hereby permitted visibility splays shall be provided in full accordance with the details indicated on the approved plan (Drawing number 1508.12.2D). The splay shall thereafter be maintained free from any obstruction exceeding 0.6 metres above the level of the adjacent highway carriageway. The reason for the condition is :- In the interests of highway safety.
6.Prior to the first occupation of the development hereby permitted the proposed accesses, on-site car parking and turning area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use. The reason for the condition is :- To ensure the permanent availability of the parking/manoeuvring area, in the interests of highway safety.
7.No works shall commence on site until such time as a Stopping Up Order to remove all highway rights subsisting in the highway land coloured brown on the attached plan has been granted and all Highway rights over the coloured land have been successfully removed. the reason for the condition is:- In the interests of ensuring a highway is not obstructed.
8.No development shall take place/commence until a Written Scheme of Archaeological Investigation has been submitted to and approved by the local planning authority in writing. The scheme shall include an assessment of significance and research questions; and 1. The programme and methodology of site investigation and recording 2. The programme for post investigation assessment 3. Provision to be made for analysis of the site investigation and recording 4. Provision to be made for publication and dissemination of the analysis and records of the site investigation 5. Provision to be made for archive deposition of the analysis and records of the site investigation 6. Nomination of a competent person or persons/organization to undertake the works set out within the Written Scheme of Investigation The reason for the condition is :- To preserve items of historical and archaeological importance as the site is within an area of high archaeological importance.
9.No development shall take place other than in accordance with the Written Scheme of Investigation approved under condition 8. The reason for the condition is :- To preserve items of historical and archaeological importance as the site is within an area of high archaeological importance.
10.The development shall not be occupied until the site investigation and post investigation assessment has been completed in accordance with the programme set out in the Written Scheme of Investigation approved under condition 8 and the provision to be made for analysis, publication and dissemination of results and archive deposition has been secured. The reason for the condition is :- To preserve items of historical and archaeological importance as the site is within an area of high archaeological importance.
11.Prior to commencement of the development hereby approved a scheme of surface water management shall be submitted to and approved by the Local Planning Authority. The development shall be carried out in accordance with the approved plans. The reason for the condition is :- To ensure adequate drainge of surface water.
12.No development shall take place until the following information has been submitted to and approved in writing by the Local Planning Authority: (i) a full site survey showing: the datum used to calibrate the site levels levels along all site boundaries levels across the site at regular intervals floor levels of adjoining buildings (ii) full details of the proposed finished floor levels of all buildings and hard surfaces. The development shall be carried out only in accordance with the approved details. No development shall take place until full details of the finished levels, above ordnance datum, of the ground floors of the proposed buildings, in relation to existing ground levels have been submitted to and approved by the Local Planning Authority. The development shall be carried out in strict accordance with the levels approved. The reason for the condtions is:- To ensure that the development takes place in the manner contemplated by the Local Planning Authority and to retain control over any significant changes in levels within the site.
13.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any order revoking and re-enacting the order) no extensions shall be built into the walls or roof of the buildings without the prior consent of the Local Planning Authority. The reason for the condition is:- In the interests of the residential amenities of the occupiers of the adjacent property.
14.No work shall commence until the exact types and colours of the materials used have been submitted to and approved by the Local Planning Authority. The details submitted shall include all materials used in the external walls and roof as well as full details of the windows and doors. The development shall be carried out using the agreed materials. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of the materials have not been submitted.
15.Prior to commencement of the development hereby approved full details of the boundary treatments including the size, type and materials shall be submitted to and approved by the Local Planning Authority. The development shall be carried out in accordance with the approved details. The reason for the condition is :- In the interests of visual amenity.
16.No development shall take place until there has been submitted to and approved by the Local Planning Authority a scheme of landscaping, which shall include indications of all existing trees and hedgerows on the land, and details of any to be retained, together with measures for their protection in the course of development. The reason for the condition is:- In the interests of the visual amenities of the locality.
17.All planting, seeding or turfing comprised in the approved details of landscaping shall be carried out in the first planting and seeding season following the occupation of the buildings or the completion of the development, whichever, is the sooner, and any trees or plants which within a period of 5 years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written consent to any variation. The reason for the condition is:- In the interests of the visual amenities of the locality.
18.Construction work shall not take place outside the following hours:- 08:00 to 18:00 Monday to Friday 08:30 to 13:30 Saturday and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
19.Prior to the commencement of the development and to the satisfaction of the Environmental Health Manager, a phase 1 contamination report shall be carried out to assess whether the land is likely to be contaminated. The report shall also include details of known previous uses and possible contamination arising from those uses. If contamination is suspected to exist, a phase 2 site investigation is to be carried out to the satisfaction of the Environmental Services Group Manager. If the phase 2 site investigation determines that the ground contains contaminants at unacceptable levels then the applicant is to submit a written strategy detailing how the site is to be remediated to a suitable standard for its proposed end use. No dwellings/buildings hereby permitted shall be occupied until the remediation works agreed within the scheme have been carried out to the satisfaction of the Local Planning Authority. The reason for the condition is :- To ensure that risks from land contamination to the future users of the land and neighbouring land are minimised, together with those controlled waters, property and ecological systems.
20.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria outlined in saved policy HOU07 of the Borough Wide Local Plan and policies CS2, CS3 and CS9 of the adopted Core Strategy.
21.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF.
22.This development involves works within the public highway that can only be carried out by Norfolk County Council as Highway Authority unless otherwise agreed in writing. It is an OFFENCE to carry out any works within the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. Please note that it is the applicant's responsibility to ensure that, in addition to planning permission, any necessary consents or approvals under the Highways Act 1980 and the New Roads and Street Works Act 1991 are also obtained from the County Council. Advice on this matter can be obtained from the County Council's Highway Development Management Group. Please contact 0344 800 8020. If required, street furniture will need to be repositioned at the applicant's expense. Public Utility apparatus may be affected by this proposal. Contact the appropriate utility service to reach agreement on any necessary alterations, which have to be carried out at the expense of the developer.
23.This proposal involves excavations adjacent to the public highway. It is an OFFENCE to carry out any works that may affect the Public Highway, which includes a Public Right of Way, without the permission of the Highway Authority. Please note that it is the applicant's responsibility to ensure that, in addition to planning permission, any necessary consents or approvals under the Highways Act 1980 and the New Roads and Street Works Act 1991 are also obtained from the County Council.
24.The imposition of the above condition does not in any way infer that Norfolk County Council, as Local Highway Authority, will support a formal application for a Stopping Up Order to remove highway rights. In addition, statutory undertakers have a right to object to the granting of a Stopping Order, which may prevent this development from progressing in its current format.
25.Please be aware it is the applicants responsibility to clarify the boundary with the public highway. Private structures such as fences or walls will not be permitted on highway land. The highway boundary may not match the applicants title plan. Please contact the hgihway research team at highway.boundaries@norfolk.gov.uk for further details.
26.NOTES - Please read the following notes carefully:- Please read the consultation response from Essex and Suffolk Water dated 10 July 2017. There are Essex and Suffolk Water Assets in the site. They have provided a list of conditions when working within the vicinity of their pipes including the requirement to inform them as per their information sheet. If you have any questions please contact Essex and Suffolk Water. Please read the consultation response by the Norfolk Constabulary dated the 07 July 2017 with recommendations relating to security.