1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the application form received by the Local Planning Authority on 9 December 2015 and the revised plan (referenced NH/15/54/1 rev A) received on 25 February 2016. The reason for the condition is :- For the avoidance of doubt.
3.The use hereby approved shall be used for holiday purposes only. The reason for the condition is :- To ensure the holiday property are not used as permanent residential accommodation.
4.Prior to commencement of the use hereby permitted any access gate(s), bollard, chain or other means of obstruction shall be hung to open inwards, set back and thereafter retained a minimum distance of 5 metres from the near channel edge of the adjacent carriageway. The reason for the condition is :- To enable vehicles to safely draw off the highway before the gate(s) or obstruction is opened.
5.Prior to the commencement of the use hereby permitted a visibility splay measuring 2.0 X 30 metres shall be provided to the eastern side of the access where it meets the highway and such splays shall thereafter be maintained free from any obstruction exceeding 0.225 metres above the level of the adjacent highway carriageway. The reason for the condition is :- In the interests of highway safety.
6.Prior to the commencement of the use hereby permitted sufficient space shall be provided within the site to enable 5 standard size family cars to turn and re-enter the highway in a forward gear. This area shall be levelled, surfaced and drained in accordance with a detailed scheme submitted to and approved in writing by the Local Planning Authority, in consultation with the Highway Authority, and thereafter available for that specific use. The reason for the condition is :- In the interests of satisfactory development and highway safety.
7.No work shall commence until the exact types, materials and colours of the windows and rooflights have been submitted to and approved by the Local Planning Authority. The development shall be carried out using the agreed materials. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of the materials have not been submitted.
8.Prior to commencement of the use hereby approved a scheme for bin storage shall be submitted to and approved by the Local Authority, bins should be provided prior to the occupancy. The reason for the condition is :- To ensure adequate storage of waste in the interest of visual amenity.
9.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria outlined in policy BNV18 and TR16 of the Great Yarmouth Borough Wide Local Plan 2001 and policy CS8 and CS9 of the Core Strategy adopted date 2016.
10.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF.