1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the details contained in the planning application forms, Design and Access Statement and drawing no's. 7280 SO1, 7280 O5 rev. C and 7280 O6 rev. A received by the Local Planning Authority on 10th December 2015. The reason for the condition is :- For the avoidance of doubt.
3.No work shall commence on the development hereby permitted until details of the surfacing and boundary treatments to the public footpath have been submitted to and approved by the Local Planning Authority in consultation with the Highway Authority. The footpath shall be constructed in accordance with the approved details before the building hereby permitted is first brought into use. The reason for the condition is :- To ensure the footpath is completed to a suitable standard.
4.The section of the existing footpath which is to be diverted shall not be altered or obstructed in any way until the new path has been fully constructed in accordance with the approved details and to the satisfaction of the Local Planning Authority in consultation with the Highway Authority. The reason for the condition is :- In order to maintain the existing Public Right of Way until an alternative route is in place.
5.Prior to the commencement of the development, a flood response plan shall be submitted to and agreed in writing with the Local Planning Authority. This flood response plan, including information regarding the availability of the Environment Agency's "Floodline Warnings Direct" flood warning scheme, shall be made available to future occupiers of the site. The reason for the condition is :- In accordance with the recommendations of the flood risk assessment, to minimise the risk to the occupants in the event of flooding.
6.No works shall commence on site until details of the surface water drainage have been submitted to and approved by the Local Planning Authority. The development shall be carried out using the drainage system as approved. The reason for condition is:- To ensure the satisfactory drainage of the site.
7.Prior to the first occupation of the development hereby permitted, any access gate(s), bollard, chain or other means of obstruction shall be hung to open inwards and set back a minimum distance of 15 metres from the near channel edge of the adjacent carriageway. Any sidewalls/fences/hedges adjacent to the access shall be splayed at an angle of 45 degrees from each of the (outside) gateposts to the front boundary of the site. The reason for the condition is :- To enable vehicles to safely draw off the highway before the gate(s) or obstruction is opened.
8.Prior to the first occupation of the development hereby permitted, the proposed access, on-site car and cycle parking, servicing and turning areas shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use. The reason for the condition is :- To ensure the permanent availability of the parking/manoeuvring area, in the interests of highway safety.
9.The development hereby permitted shall be carried out incorporating the measures to mitigate the risk from flooding set out in the Fllod Risk Assessment submitted with the application. The reason for the condition is :- To ensure that mitigation measures are undertaken as the building is located within an area at risk of flooding.
10.REASON FOR APPROVAL OF THE APPLICATION :- The proposal is an appropriate use for the industrial estate.
11.NOTES - Please read the following notes carefully:- a) This planning permission does not convey consent for the diversion or closure of the existing right of way for which a separate order under section 257 of the Town and Country Planning Act 1990 needs to be made. b) The Environmental Health Officer has advised that the site is within 250 metres of a former landfill site and the building should be designed to take into account the possible presence of landfill gas.