| No. | Condition Text |
|---|
| 1. | The works of demolition hereby authorised must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The works of demolition shall be carried out in accordance with the application form and approved plan received by the Local Planning Authority on 28th September 2015.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | No demolition/development shall take place until a contract for the carrying out of the works of redevelopment of the site has been made and the reserved matters have been approved by the Local Planning Authority for the redevelopment for which the contract provides.
The reason for the condition is :-
In order for the Local Planning Authority to retain control over the use of the site. |
| 4. | No demolition/development shall take place until a method statement/demolition plan is submitted to, and approved in writing by, the Local Planning Authority. The method statement/demolition plan shall provide details relating to how the demolition will be carried out, materials haulage from the site, highway protection and pedestrian protection/diversions.
The reason for the condition is :-
In the interests of highway and pedestrian safety. |
| 5. | Demolition/Development shall not commence until a scheme detailing provision for on site parking for construction workers for the duration of the demolition/construction period has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be implemented throughout the demolition/construction period.
The reason for the condition is :-
To ensure adequate off street parking during construction in the interests of highway safety. |
| 6. | Prior to the commencement of any works a Construction Traffic Management Plan and Access Route which shall incorporate adequate provision for traffic management / control, temporary signing and for addressing any abnormal wear and tear to the highway shall be submitted to and approved in writing by the Local Planning Authority in consultation with Norfolk County Council Highway Authority together with proposals to control and manage construction traffic using the 'Construction Traffic Access Route' and to ensure no other local roads are used by construction traffic.
The reason for the condition is :-
In the interests of maintaining highway efficiency and safety. |
| 7. | For the duration of the demolition/construction period all traffic associated with the demolition/construction of the development will comply with the Construction Traffic Management Plan and use only the 'Construction Traffic Access Route' and no other local roads unless agreed in writing by the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
In the interests of maintaining highway efficiency and safety. |
| 8. | The demolition works shall not take place outside the following hours:-
Monday to Friday 08.00-18.00 hours
Saturdays 08.30-13.30 hours
No working on Sundays or bank holidays.
The reason for the condition is :-
The interests of the amenities of the neighbouring properties. |
| 9. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |
| 10. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria of Policy BNV16 of the Great Yarmouth Borough-Wide Local Plan 2001. |