Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development hereby approved shall be carried out in accordance with the revised plans received by the Local Planning Authority on the 16th December 2015 referenced 4403 708, 4403 709, 4403 711, 4403 702 A, 4403 701 A, 4403 700 B, 4403 706 A, the revised plan received the 21st December 2015 referenced 4403 700 C, the Drainage Strategy Report received the 1st February 2016 and all other forms, additional information and plan referenced 4403 710 received on the 23rd October 2015. The reason for the condition is:- To ensure a satisfactory form of development.
3.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking and re-enacting the order) no extensions shall be built at the dwellings on plots 15/E and 14/E without the prior consent of the Local Planning Authority. The reason for the condition is:- To ensure that adequate curtilage is retained to serve the dwelling and to protect the amenities of the occupiers of the adjoining dwelling.
4.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking and re-enacting the order) no fencing shall be erected around the front garden areas of the dwellings hereby permitted without the consent, in writing, of the Local Planning Authority. The reason for the condition is:- In the interests of the visual amenities of the area.
5.No works shall commence on the site until such time as detailed plans of the roads, footways, foul and surface water drainage have been submitted to and approved in writing by the Local Planning Authority in consultation with the Highway Authority. All construction works shall be carried out in accordance with the approved plans. The reason for the condition is:- To ensure satisfactory development of the site and a satisfactory standard of highway design and construction.
6.No works shall be carried out on roads, footways, foul and surface water sewers otherwise than in accordance with the specifications of the Local Planning Authority in consultation with the Highway Authority. The reason for the condition is:- To ensure satisfactory development of the site and to ensure estate roads are constructed to a standard suitable for adoption as public highway.
7.Before any dwelling is first occupied the road(s) and footway(s) shall be constructed to binder course surfacing level from the dwelling to the adjoining County road in accordance with the details to be approved in writing by the Local Planning Authority in consultation with the Highway Authority. The reason for the condition is:- To ensure satisfactory development of the site.
8.Prior to the commencement of any works on site a Construction Traffic Management Plan, to incorporate details of on-site parking for construction workers, access arrangements for delivery vehicles and temporary wheel washing facilities for the duration of the construction period shall be submitted to and approved in writing with the Local Planning Authority in consultation with Norfolk County Council Highway Authority. The reason for the condition is:- In the interests of maintaining highway efficiency and safety.
9.For the duration of the construction period all traffic associated with the construction of the development will comply with the Construction Traffic Management Plan and unless otherwise approved in writing with the Local Planning Authority in consultation with the Highway Authority. The reason for the condition is:- In the interests of maintaining highway efficiency and safety.
10.Prior to the commencement of the development of plots 2A, 3/A, 5/F, 6/F, 7/F and 8/F a tree protection plan shall be submitted to and approved by the Local Planning Authority. Prior to the commencement of the development of plots 2A, 3/A, 5/F, 6/F, 7/F and 8/F the tree protection plan shall be implemented in accordance with the approved details and shall be carried out for the duration of the development. The reason for the condition is:- To protect the trees which are worthy of retention.
11.No works to or removal of trees shall be undertaken for a period of five years from the date of this permission other than in accordance with the Arboricultural Impact Assessment received by the Local Planning Authority on the 23rd October 2015. The reason for the condition is:- To protect the trees which are worthy of retention in the interest of the amenity of the area.
12.The development shall not be occupied until the post investigation assessment has been completed in accordance with the programme set out in the approved archaeological written scheme of investigation submitted in support of the planning application, and the provision for analysis, publication and dissemination of results and archive deposition has been secured. The reason for the condition is:- To comply with National Planning Policy Framework paragraph 141.
13.Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking and re-enacting the order) no openings shall be inserted into the roof slopes of any of the dwellings hereby permitted without the consent, in writing, of the Local Planning Authority. The reason for the condition is:- In the interests of the visual amenities of the area.
14.Prior to the commencement of the development hereby permitted details of an acoustic screen to the western boundary shall be submitted to and approved by the Local Planning Authority in consultation with the Group Manager Environmental Health. The screen shall be erected prior to the occupation of any of the dwellings hereby approved. The reason for the condition:- In the interest of the amenities of the future occupiers of the development.