| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the application form, approved plans (drawing number 01, 02, 03, 04 and 05)and additional information including the Quantum Heating and Koster Waterproofing Systems received by the Local Planning Authority on 7th August 2015 and the further information received by the Local Planning Authority on the 26th October 2015.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | Prior to the installation of the Secondary Glazing details of the method used to insert the secondary glazings into the property shall be received in writing and agreed by the Local Planning Authority. The insertion of the window shall be carried out in accordance with the approved details and the type of secondary glazing shall be undertaken to the specification outlined in the information received on the 26th October 2015.
The reason for the condition is :-
The submitted details did not effectively demonstrate how the building would benefit and not suffer from the window installation. |
| 4. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria outlined in policy BNV5 of the Borough Wide Local Plan. |
| 5. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |