1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with drawing no. Gl001MHF.PDF received by the Local Planning Authority on 8th June 2015. The reason for the condition is :- For the avoidance of doubt.
3.Prior to commencement of use, the access gates shall be hung to open inwards, and together with the supporting brick piers, be set back and thereafter maintained a minimum distance of 2.4 metres from the near channel edge of the adjacent carriageway. The reason for the condition is :- In the interests of highway safety.
4.The proposed driveway surface shall be constructed of porous or permeable materials, or provision shall be made to direct run-off water to a porous or permeable area within the grounds of the house. The reason for the condition is :- To minimise the risk of flooding and to prevent the discharge of surface water onto the public highway.
5.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF.
6.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for domestic additions set out in Policy HOU18 of the adopted Great Yarmouth Borough-wide Local Plan.