| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The annex hereby permitted shall be incidental to the use of the main dwelling 11 North Road Ormesby and shall not be occupied at any time as a separate un-associated unit of accommodation.
The reason for the condition is :-
In the interest of highway safety such that vehicle movements are restricted to the use associated with the development. |
| 3. | The development shall be carried out in accordance with the plans and forms received by the Local Planning Authority on the 16th February 2015.
The reason for the condition is :-
For the avoidance of doubt. |
| 4. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order revoking and re-enacting the order) no windows or openings other than those shown on the approved plans shall be inserted into the walls or roof of the building nor shall the building be extended in anyway.
The reason for the condition is:-
In the interests of the residential amenities of the occupiers of the adjacent property. |
| 5. | Prior to the commencement of the development hereby permitted the top 300mm of soil within the building shall be excavated, removed from site and disposed of.
The reason for the condition is:-
To reduce the risk of contamination being present. |
| 6. | Following the removal of soil in accordance with condition 5 of this permission and prior to the commencement of the development the exposed ground within the building is to be capped and a non-permeable membrane installed to cover the whole ground floor level.
The reason for the condition is:-
To reduce the risk of contamination permeating the annex. |
| 7. | All potable water pipes that pass through the ground underneath the annex hereby approved are to be encased in protectaline barrier pipe to BS EN 1057:1996 standards.
The reason for the condition is:-
To reduce the risk of contamination permeating the water supply. |
| 8. | No work should take place on the site outside of the following hours:
07:30 to 18:00 hours Monday to Friday
08:30 to 13:30 hours Saturday
No working on Sundays and bank holidays.
The reason for the condition is:-
In the interests of the residential amenities of the adjacent properties. |
| 9. | The boarding shown on the approved plan to the south east elevation of the balcony is to be erected prior to occupation of the annex and is to remain in perpetuity.
The reason for the condition is:-
In the interests of the residential amenities of the adjacent properties. |
| 10. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria set out in Policy HOU8, BNV10, HOU15 and HOU16 of the adopted Great Yarmouth Borough-wide Local Plan. |
| 11. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |