| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development hereby permitted shall be carried out entirely in accordance with the details shown on the application forms received by the Local Palnning Authority on 19th December 2014 and amended drawings received by the Local Planning Authority on 18th February 2015.
The reason for the condition is :-
For the aoidance of doubt. |
| 3. | Building work to carry out the conversion on shall not be carried on outside the following hours:-
0730 hours to 1800hrs Mondays to Fridays
0830 hours to 1330 hours Saturdays and no work on Sundays or Bank Holidays.
The reason for the condition is:-
In the interests of the residential amenities of the occupiers of the nearby property. |
| 4. | The 900mm wide gate shown on the approved plan to access the wheelie bin storage shall be erected prior to the occupation of the dwellings hereby approved.
The reason for the condition is:-
To ensure adequate bin storage is provided. |
| 5. | The area designated as bin storage on the approved plans shall be retained as bin storage for use by occupiers of the dwellings hereby approved and shall remain available for this use in perpetuity.
The reason for the condition is:-
In the interests of the amenity of the area. |
| 6. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |
| 7. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria set out in policies HOU22 and HOU23 of the adopted Great Yarmouth Borough-wide Local Plan. |