| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the revised plans 12-0040/201 Rev C, 12-0040/202 Rev B, 12-0040/203 Rev A, 12-0040/204 Rev B & 12-0040/205 Rev C received by the Local Planning Authority on 7th May 2014 and the Arboricultural Survey/Tree Report and asscoiated plans recieved on the 23rd July 2013 unless first submitted to and approved in writing by the local planning authority.
The reason for the condition is:-
For the avoidance of doubt. |
| 3. | The building hereby permitted shall not be occupied at any time other than for purposes ancillary to the residential dwelling known as Heartherbrae, Herringfleet Road, St Olaves. The building shall at no time be used as a separate dwelling or let separately for holiday purposes.
The reason for the condition is :-
This permission is granted under exceptional circumstances for a form of development not normally permitted by the Local Planning Authority and to enable the Authority to retain control over the use of the site.
|
| 4. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria for domestic additions set out in Policies NNV2, BNV18 and HOU18 of the adopted Great Yarmouth Borough-wide Local Plan. |
| 5. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |