| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development hereby permitted shall be carried out entirely in accordance with the details shown on the application forms and plans received by the Local Planning Authority on 28th February 2014, together with the information shown on drawing A4 01 and accompanying letter received by the Local Planning Authority on 17th July 2014.
The reason for the condition is:-
For the avoidance of doubt and to ensure the development is carried out with the correct documentation. |
| 3. | Prior to the first occupation of the accommodation hereby permitted details of the extent, type and colour of the render to be applied on any external surface of the building shall be submitted for the approval of the Local Planning Authority and all such work as agreed carried out in accordance with such details as may be agreed, prior to the first occupation and the finishes shall thereafter maintained in accordance with the approved details.
The reason for the condition is:-
In the interests of the appearance of the building in the Conservation Area as precise details of external finishes were a part of the original submission.
|
| 4. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 ( or any order revoking and re-enacting that Order) the dwelling shall not be extended in any way and no additional windows or other opening inserted into the wall or roof without the prior consent of the Local Planning Authority.
The reason for the condition is:-
To enable the Local Planning Authority to retain control over any extensions to the dwellings in the interests of residential amenity and the appearance of the building in the Conservation Area. |
| 5. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new housing development set out in Policies HOU7 of the adopted Great Yarmouth Borough-wide Local Plan |
| 6. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |