| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development hereby permitted shall be carried out in accordance with the application form and plans received on 25th June 2013 unless first submitted to and approved in writing by the local planning authority.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | No works shall commence on site until a scheme for the parking of cycles has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be fully implemented before the development is first occupied or brought into use and thereafter retained for this purpose.
The reason for the condition is:-
To ensure the provision of adequate cycle parking that meets the needs of occupiers of the proposed development and in the interests of encouraging the use of sustainable modes of transport.
|
| 4. | No part of the proposed structure (to include fascia board / rainwater goods and guttering) shall overhang or encroach upon highway land and no gate / door / ground floor window if installed shall open outwards over the highway.
The reason for the condition is:
In the interests of highway safety.
|
| 5. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new housing development set out in Policies HOU7 and HOU15 of the adopted Great Yarmouth Borough-wide Local Plan |
| 6. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |