Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- Required to be imposed pursuant to Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the plans and Drawing Nos.01-02-13-1-1-115409 Rev P-,01-02-13-1-1-115412 P-,01-02-13-1-1-115414 Rev P-, 01-02-13-1-1-115414 RevP-,01-02-13-1-1-115415 Rev P-,01-02-13-1-1-115416 Rev P- 01-02-13-1-1-115417 Rev P-,01-02-13-1-1-115418 Rev P-,Design and Access Statement, Planning Statement,Arboriculture survey and recommendations Ecological survey and enhancement measures in List A and B, received by the Local Planning Authority on 22 May 2013 and application form. The reason for the condition is :- For the avoidance of doubt and in accordance with the submitted details
3.Prior to the first occupation of the development hereby permitted the proposed access, on- site car parking and turning area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use. The reason for the condition is :- To ensure the permanent availabilty of the parking/manoeuving area, in the interests of highway safety.
4.There shall be no restriction on the use of the car parking spaces(numbered 5,6,7,8 and 9 shown on the approved plan(Drawing No. 13-1-1-1154-NPS-DR-A 13 Rev P-) by occupers of , or visitors to, any of the builidngs hereby permitted The reason for the condition is :- To minimise the potential for on-street parking and thereby safeguard the interest of safety and convenience of road users.
5.No development shall take place until the applicant or their agents or successors in title has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation including a timetable which has been previously submitted to and approved in writing by the local planning authority: A) No development shall take place/commence until a Written Scheme of Investigation has been submitted to and approved by the local planning authority in writing. The scheme shall include an assessment of significance and research questions; and 1. The programme and methodology of site investigation and recording 2. The programme for post investigation assessment 3. Provision to be made for analysis of the site investigation and recording 4. Provision to be made for publication and dissemination of the analysis and records of the site investigation 5. Provision to be made for archive deposition of the analysis and records of the site investigation 6. Nomination of a competent person or persons/organization to undertake the works set out within the Written Scheme of Investigation B) No demolition/development shall take place other than in accordance with the Written Scheme of Investigation approved under condition (A). C) The development shall not be occupied until the site investigation and post investigation assessment has been completed in accordance with the programme set out in the Written Scheme of Investigation approved under condition (A) and the provision to be made for analysis, publication and dissemination of results and archive deposition has been secured. The Historic Environment Service will provide a brief for these works on request. The reason for the condition is :-In accordance with Paragraph 141 of the NPPF.
6.All planting comprised in the approved details of landscaping shall be carried out in the first planting season following the occupation of each of the dwellings and any trees or plants which within a period of 5 years from the completion of the development die, are removed or become seriously damaged or diseased shall be replaced in the next planting season with others of similar size and species, unless the Local Planning Authority gives written consent to any variation. The reason for the condition is :- In the interests of the visual amenities of the locality and the submitted plans.
7.STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF
8.The Reason for the Approval. The local planning authority considers that the application complies with Policy HOU7 HOU15,HOU16 and HOU17 of the Great Yarmouth Borough Wide Local Plan 2001.