| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | No work shall commence until the exact type and colour of the materials have been submitted to and approved by the Local Planning Authority.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of the materials have not been submitted. |
| 3. | The development hereby permitted shall be carried out in accordance with the application form, plans, Design & Access Statement and Flood Risk Assessment received on 28th December 2012 unless first submitted to and approved in writing by the local planning authority.
The reason for the condition is :-
For the avoidance of doubt. |
| 4. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking or re-enacting that Order)(with or without modification), there shall be no additional window or other opening constructed at first floor level or above in any elevation of the development hereby approved without the prior written permission of the local planning authority.
The reason for the condition is :-
To help safeguard the privacy and amenity of the occupiers of adjacent properties.
|
| 5. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any Order revoking and re-enacting that Order)(with or without modification), no extensions, roof alterations, porches or ancillary buildings as defined within Classes A, B, C, D & E of Part 1 Schedule 2 of that Order shall be erected or brought onto the land unless an appropriate planning application is first submitted to and approved by the local planning authority.
The reason for the condition is :-
In the interests of the satisfactory appearance of the development and the amenities of adjoining residents.
|
| 6. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new housing development set out in Policies HOU7, HOU15 & HOU17 of the adopted Great Yarmouth Borough-wide Local Plan. |
| 7. | NOTES - Please read the following notes carefully:-
The applicant is advised that Essex & Suffolk Water have mains which appear to be within the vicinity of the proposed development. They wish to protect their apparatus and therefore any future applications submitted for this site may prompt them to comments as they cannot accept any buildings or structures within 3 metres either side of the main, which is protected by an easement.
If the applicant/agent requires a copy of the asset record plan this can be supplied on receipt of a written request quoting reference number PG/PA/13/006.
|
| 8. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |