1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The extension hereby permitted shall be carried out in accordance with the application form & plans received on 24th August 2012 unless first submitted to and approved in writing by the local planning authority. The reason for the condition is :- For the avoidance of doubt.
3.No development shall take place until a scheme for all external finishes and works of repair to both the new extension and the existing garage has been submitted to and approved in writing by the local planning authority. The development shall be carried out entirely in accordance with the details as approved. The reason for the condition is :- To ensure the satisfactory appearance of the development and to ensure the visual amenities of adjacent occupants are maintained and improved.
4.If it transpires that any part of the proposed extension, including rainwater goods/guttering and fascia boards would encroach upon or overhang the adjoining property, the consent of the owner(s) of that property must first be obtained. The reason for the condition is:- To ensure that the adjacent property is encroached upon.
5.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for domestic additions set out in Policy HOU18 of the adopted Great Yarmouth Borough-wide Local Plan.
6.NOTES - Please read the following notes carefully:- The applicant is advised to note the proximity of the mains services which run between the application site and the adjacent dwelling. The contractor/builder should contact Building Control Officers to ascertain if there is any potential imapct on these services caused by the construction. In addition to the above at no time shall any shrubs, trees or other planting be removed from the neighbouring site without the agreement of the occupant of the adjacent property, nor should the contractor/builder enter the site for construction, or any other purposes without the express consent of said neighbour.