| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development hereby permitted shall be carried out in accordance with the application form and Design & Access Statement submitted on 4th July 2012 and amended plans numbered 673/4A submitted on 13th August 2012 and plans numbered 673/3A & 673/3B submitted on 14th September 2012 unless submitted to and approved in writing by the local planning authority.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | No construction works shall occur outside the following hours:
08:00 to 18:00 hours Monday to Friday
08:30 to 13:30 hours Saturdays
No works shall take place on sundays or Bank Holidays
The reason for the condition is :-
To ensure the amenities of nearby residents are maintained. |
| 4. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new housing development set out in Policies HOU7 and HOU15 of the adopted Great Yarmouth Borough-wide Local Plan |
| 5. | NOTES - Please read the following notes from Environmental Health carefully:-
NOISE:
The internal structure of the building must provide adequate noise attenuation between the residential accommodation and the communal areas and from external noise.. The levels of insulation should be in accordance with the current Building Regulations.
ROOM SIZES:
The internal dimensions of all rooms within the proposed self-contained flats shall comply with the minimum requirements of the Council's standards for this type of property and expected occupancy of each dwelling. A copy of these standards is available from Environmental Health.
VENTILATION:
Adequate mechanical ventilation must be provided to the shower room and kitchen area. Mechanical ventilation must have a 'whisper-quiet' operation and meet or exceed current Building Regulations.
LOCAL AIR QUALITY:
The site will potentially generate a significant amount of dust during the construction process; therefore, the following measures should be employed:-
- An adequate supply of water shall be available for suppressing dust.
- Mechanical cutting equipment with integral dust suppression should be used.
- There should be no burning of any materials on site.
ADVISORY NOTE:
The applicant is strongly recommended to advise neighbouring businesses and any residential occupiers of the proposals, together with contact details in the event of problems.
|