| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is:-
Required to be imposed pursuant to Section 18 of the Planning (Listed Building and Conservation Areas) Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development hereby permitted shall be carried out in accordance with the application form, plans and Flood Risk Assessment received by the local planning authority on 29th May 2012 and the Flood Response Plan recevied on 3rd October 2013 and any other documentation submitted in relation to the application, unless first submitted to and agreed in writing by the local planning authoirty.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | All existing ornamental features including any chimney pieces, plasterwork, architraves, skirting, panelling, doors, staircases, balustrading etc shall remain undisturbed in their existing position and shall be fully protected during the course of the work on the site, unless specifically authorised otherwise on the drawings hereby approved of susequently in writing by the local planning authority prior to any commencement of works on the site.
The reason for the condition is :-
To ensure the protection of the special architectural and historic interest of the building. |
| 4. | All external and internal works and finishes and works of making good shall match the existing original work in respect of materials used, detailed execution and finished appearances except where indicated otherwise on the drawing hereby approved.
The reason for the condition is :-
To ensure the protection of the special architectural and historic interest of the building. |
| 5. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria of policies BNV5, BNV6, BNV10, HOU7 & HOU15 of the adopted Great Yarmouth Borough Wide Local Plan. |
| 6. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |