| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with drawing no. PL01 received by the Local Planning Authority on 27th September 2012.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | The dwelling shall be constructed with finished floor levels set at, or above, 0.95m AOD.
The reason for the condition is :-
To ensure the flood risk to people and property is adequately mitigated for. |
| 4. | The dwelling shall be constructed and completed in accordance with ODPM guidance "Preparing for Floods".
The reason for the condition is :-
To minimise the damage to the development in the event of flooding. |
| 5. | All habitable accommodation shall be situated above 3.23m AOD.
The reason for the condition is :-
To minimise the risk to life in the event of flooding. |
| 6. | The flood response plan submitted with the application should be made available to future occupiers of the site by means of a fixed notice within the dwelling prior to habitation.
The reason for the condition is :-
To minimise the risk to the occupants in the event of flooding. |
| 7. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposals meet the criteria for new housing development set out in Policies HOU7 and HOU15 of the adopted Great Yarmouth Borough-wide Local Plan |
| 8. | STATEMENT OF POSITIVE ENGAGEMENT: In dealing with this application Great Yarmouth Borough Council has actively sought to work with the applicant in a positive and proactive manner, in accordance with paragraphs 186 and 187 of the NPPF. |