1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development shall be carried out in accordance with the revised plans 1427-D03 Rev C, 1427-D-04 Rev A, 1427-D-05 Rev C & 1427-D-06 Rev A received by the Local Planning Authority on 11th April 2012. The reason for the condition is:- For the avoidance of doubt.
3.The materials to be used in the external finishes of the extension hereby permitted shall match those used in the existing building, unless submitted to and agreed in writing by the local planning authority. The reason for the condition is :- For the avoidance of doubt.
4.No development on the extension hereby approved shall be carried out outside the following hours: 07:30 to 18:00 Monday to Friday 08:00 to 13:00 Saturday Other hours including Sundays and Bank Holidays, no work producing audible noise at the nearest noise sensitive property. Every effort should be made to reduce the impact of dust generation to local residential properties and commercial busniesses, in the proximity of the development. Where possible, a supply of water protected against frost should be available to address this problem; alternatively, erection of hoardings to prevent dust travel must be considered. The reason for the condition is :- To ensure the amenitites of adjacent occupants are not affected to any significant and unacceptable degree.
5.The construction of the extension hereby permitted shall not be carried out between the following dates: 1st April to 30th September The reason for the condition is :- To ensure the amenities of the adjacent holiday park are not unduly disturbed during the main holiday season and in accordance with the agents letter dated 11th April 2012.
6.No works shall commence on site until such time as details of the slab levels of the extension in relation to existing ground levels have been submitted to and approved by the Local Planning Authority. The reason for the condtions is:- To ensure that the development takes place in the manner contemplated by the Local Planning Authority and to retain control over any significant changes in levels within the site.
7.Prior to the commencement of the use hereby permitted the proposed on-site car parking & servicing / turning areA shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use. The reason for the condition is: To ensure the permanent availability of the parking manoeuvring area, in the interests of highway safety.
8.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for alterations and extensions to buildings set out in Policy BNV18 of the adopted Great Yarmouth Borough-wide Local Plan