| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The current and any subsequent owners, are responsible for erecting suitable permanent warning notices detailingthe nature of the flood risk and the flood plan for this site. Furthermore, a fixed sign shall be displayed permanently at each entrance to the site giving this information. All signs shall be kept legible, clear of obstruction and up-to-date if flood risk information changes.
The reason for the condition is :-
To ensure that the occupants of the development are aware that the site is at risk of flooding. |
| 3. | Prior to the commencement of the development, a flood response plan shall be submitted to, and agreed in writing with, the Local Authority. The flood response plan' including information regarding the availability of the Environment Agency's 'Floodline' flood warning scheme, shall be made available to future occupants of the site by means of a fixed notice within the building prior to use hereby permitted commencing.
The reason for the condition is :-
To ensure that occupants of the development are safe in the event of a flood as is set out in PPS25 paragraph E3. |
| 4. | The development shall have a minimum finished floor level of no lower than 2.43m AOD.
The reason for the condition is :-
To ensure the development remains dry in the event of flooding for the adequate protection of the occupants as is set out in PPS25 Table D.1. |
| 5. | Prior to the commencement of the development details shall be submitted for car and cycle parking in accordance with the adopted standard of the Local Planning Authority and works in accordance with such details as may be agreed shall be completed and available for use prior to the use hereby permitted first commencing.
The reason for the condition is :-
To ensure the provision of adequate parking to serve the proposed development. |
| 6. | No part of the proposed structure shall overhang or encroach upon highway land and no door or window shall open outwards over the public footway.
The reason for the condition is :-
To prevent obstruction of the public footway in the interests of highway safety.
|
| 7. | The car park shall be laid out in accordance with the layout shown on the details shown on Middleton and George drawing no.10 submitted with application 06/08/01040/F prior to the use of the offices hereby permitted first being brought into use and the area shall thereafter be kept available for the parking of staff and visitors cars in connection with the office use.
The reason for the condition is :-
To ensure the provision of adequate parking to serve the proposed development. |
| 8. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria of Policy EMP16 of the Great Yarmouth Borough-wide Local Plan. |