| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the letter and revised plan numbered 2010-26/004 Rev D received by the Local Planning Authority on 01-04/2011.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | The existing trees on the site shall not be felled or damaged in any way without the prior consent in writing of the Local Planning Authority.
The reason for the condition is:-
The existing trees are subject to a Tree Preservation Order and as such represent an important visual amenity which the Local Planning Authority consider should be maintained. |
| 4. | No work shall commence until the exact type and colour of the materials have been submitted to and approved by the Local Planning Authority.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of the materials have not been submitted. |
| 5. | Prior to the commencement of use of the play area shown on the plans hereby approved, full details of any play equipment to be erected on the site shall be submitted to and approved in writing with the local planning authority.
The reason for the condition is :-
To ensure the satisfactory appearance of the development and to preserve the current amenities of any adjacent residential occupants. |
| 6. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the provisions of the Great Yarmouth Borough Wide Local Plan and, in particular, policies SHP7, SHP9, BNV18 & BNV20. |