| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The existing footpath shall not be altered or obstructed in any way until the new path has been fully constructed in accordance with the approved plan and to the satisfaction of the Local Planning Authority in consultation with the Highway Authority.
The reason for the condition is :-
In order to maintain the existing Public Right of Way until an alternative route is in place. |
| 3. | The development shall be carried out in accordance with the details shown on the application form and plan received by the Local Planning Authority on 17th January 2011 and the statement received by the Local Planning Authority on 10th March 2011.
The reason for the condition is :-
For the avoidance of doubt. |
| 4. | Prior to any work taking place on the diversion hereby permitted, precise details of the height and type of fencing to be installed on eastern side of the new footway and all works shall be completed in accordance with approved details.
The reason for the condition is :-
For the avoidance of doubt and as precise details have not been submitted as a part of the application. |
| 5. | NOTES - Please read the following notes carefully:-
This planning permission does not convey consent for the diversion or closure of the existing right of way for which a separate order under section 257 of the Town and Country Planning Act 1990 needs to be made.
The applicant is advised to contact NPLaw to make the diversion on behalf of Great Yarmouth Borough Council under Section 257 of the Town and Country Planning Act 1990. The applicant will have to reimburse all of Great Yarmouth Borough Council's costs in respect of this matter.
The path must be constructed to the specifications of the Highway Authority (minimum withs, surface materials etc - contact Paul Ryan - tel 01603 223317) and signed off before any works are carried out.
|