1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The development hereby permitted shall be carried out strictly in accordance with Drawing No. 3569/160 G and the Calor Gas fact sheets submitted with the application. The reason for the condition is :- To ensure the permission relates to the correct documents.
3.Before the development hereby permitted is first brought into use the 500mm boundary wall shall be erected as indicated on Drawing No. 3569/160 G. Details of the exact type and colour of the materials to used shall be submitted to and agreed in writing by the Local Planning Authority prior to its construction. The development shall be carried out in accordance with the details as approved. The reason for the condition is :- To enable the Local Planning Authority to ensure the satisfactory appearance of the development.
4.NOTES - Please read the following notes carefully:-
5.The installation must be in accordance with current industry safety standards and codes of practice. It must also comply with any requirements of the Health and safety Executive and Calor Gas. It is assumed supplies to each property will be by underground pipe. These must be so located and at such depth that they will not suffer damage from householders. A plan for future management and maintenance of the installation and underground pipework should be developed.
6.REASON FOR APPROVAL OF THE APPLICATION :- The proposal is considered to be compatible with the approved development of this site and to accord with Policy BNV10 of the adopted Great Yarmouth Borough-Wide Local Plan.