1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is:- Required to be imposed pursuant to Section 18 of the Planning (Listed Building and Conservation Areas) Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.No demolition works shall commence until a contract has been let for the development granted planning permission under reference 06/10/0183/F and details of the contract have been submitted for the agreement of the Local Planning Authority. The reason for the condition is :- In the interests of the appearance of the Conservation Area.
3.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria of Policies BNV9 and BNV10 of the adopted Great Yarmouth Borough-Wide Local Plan 2001.