1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.Prior to the commencementof the use hereby permitted on-site car parking parking and turning areas shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and shall be retained thereafter available for that specific use. The reason for the condition is :- To ensure the provision of adequate on-site parking and turning facilities for the development.
3.Prior to the commencement of the use hereby permitted a visibility splay measuring 2.4 x 59 metres shall be provided to the south of the access where it meets the highway and such splay shall thereafter be maintained free from obstruction exceeding 0.6 metres above the level of the adjacent highway carriageway. The reason for the condition is :- In the interests of highway safety.
4.Notwithstanding the provisions of Class A of Schedule 2, Part 2 of the Town and Country Planning (General Permitted Development) Order 1995, (or any Order revoking, amending or re-enacting that Order) no gates shall be erected across the approved access unless details have first been submitted to and approved in writing by the Local Planning Authority. The reason for the condition is :- In the interests of highway safety.
5.Prior to the any works commencing details of a surface water drainage system to serve the proposed new roadways shall be submitted for the approval of the Local Planning Authority and all works completed in accordance with such details as may be agreed. The reason for the condition is :- To ensure satisfactory drainage is provided for the impermeable surfaced roadway as details have not been submitted as part of the application.
6.The site shall only be used for the stationing of touring caravans for holiday purposes during the period from 28th February to 14th January in the following year. The reason for the condition is :- The site is allocated as a prime holiday site in The Great Yarmouth Borough-Wide Local Plan to ensure any units are used for any purpose contrary to this designation.
7.The development hereby permitted shall be carried out in accordance with the application form and plans received by the Local Planning Authority on 21st August 2009 unless otherwise approved in writing by the Local Planning Authority. The reason for the condition is :- For the avoidance of doubt and to ensure the satisfactory development of the site in accordance with the approved plans.son for the condition is :-
8.The existing trees and hedge on the site shall not be felled or damaged in any way, other that to allow the formation of the visibility splay, without the prior consent in writing of the Local Planning Authority. The reason for the condition is:- The existing trees represent an important visual amenity which the Local Planning Authority consider should be substantially maintained.
9.Prior to any work commencing on the site details of any external alterations to the chalets to be converted into a reception and shower block shall be submitted for the approval of the Local Planning Authority and all works completed in accordance with such details as may be agreed. The reason for the condition is :- Such details have not bee submitted as part of the application.
10.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the criteria for holiday accommodation provision and improvements as set out in Policies TR2 and TR11.