No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.Prior to the first occupation of the development hereby approved the proposed vehicular access shall be constructed in accordance with Norfolk County Council's industrial access specification and additionally to accord with details to be approved in writing by the Local Planning Authority, for the first 5 metres into the site as measured back from the near edge of the adjacent carriageway. The reason for the condition is :- To ensure satisfactory access into the site.
3.Prior to the first occupation of the development hereby permitted the access gates shall be hung to open inwards and shall be set back a minimum distance of 5 metres from the near edge of the adjoining highway carriageway. The reason for the condition is :- In the interests of highway safety.
4.Prior to the first occupation of the development hereby permitted the proposed on-site staff car parking, shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for this specific use. The reason for the condition is :- To ensure the permanent availability of the facilities in the interests of highway safety.
5.No works shall commence on site until a detailed scheme for the off-site highway improvement works as indicated on drawing no. CL01Rev P1 has been submitted to and approved in writing by the Local Planning Authority in consultation with the Highway Authority. The reason for the condition is :- To ensure that the highway improvement works are designed to an appropriate standard in the interest of highway safety and to protect the environment of the local highway corridor.
6.Prior to the first occupation of the development hereby permitted the off-site highway improvement works referred to in condition 5 shall be completed to the written satisfaction of the Local Planning Authority in consultation with the Highway Authority. The reason for the condition is :- To ensure that the highway network is adequate to cater for the development proposed.
7.Prior to the first occupation of the development hereby permitted a detailed signing scheme for the staff car park shall be submitted to and approved in writing by the Local Planning Authority in consultation with the Highway Authority and shall be implemented. The reason for the condition is :- To minimise vehicle movements in the interest of highway safety.
8.The finished ground floor level shall be set as high as possible and at a minimum of 0.84mAOD as stated within Section 5.11 of the submitted FRA. The reason for the condition is :- To ensure flood risk posed to those within the development is reduced as far as possible.
9.The proposed escape hatch shall be incorporated into the design of the development as shown in Drawing: (GA) 007. The reason for the condition is :- To ensure that a safe place of refuge above the flood level is available should evacuation measures fail to ensure the safety of occupants.
10.The impermeable area of the proposed development shall not exceed 2,250m². The reason for the condition is :- To ensure surface water flood risk posed to occupants of the development is decreased.
11.The proposed development shall adopt the Flood Response Plan submitted within Appendix G of the FRA. The reason for the condition is :- To ensure the safety of current and future occupants of the proposed development.
12.The current and any subsequent owners, are responsible for erecting suitable permanent warning notices detailing the nature of the flood risk posed to this site. All signs shall be kept legible, clear of obstruction and up-to-date if flood risk information changes. The reason for the condition is :- To ensure that the owners and visitors of the site are aware that the land is at risk of flooding.
13.Construction work shall not take place outside the following hours:- 07:30 to 18:00 Monday to Friday 08:00 to 13:00 Saturday and no work shall take place on Sundays or Bank Holidays. (These hours shall only apply to work generating noise that is audible at the boundary of the nearest noise sensitive property) The reason for the condition is :- In the interests of the residential amenities of the occupiers of nearby dwellings.
14.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the requirements of Policy BNV16 of the Great Yarmouth Borough-Wide Local Plan.
15.NOTES - Please read the following notes carefully:-
16.The applicant's attention is drawn to the attached letters from Anglian Water and Natural England and the need to comply fully with their requirements.