| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The materials to be used on the development hereby permitted shall accord with the details submitted on the application form and accompanying plans, unless otherwise agreed in writing with the local planning authority.
The reason for the condition is :-
To ensure the satisfactory appearance of the development. |
| 3. | No development shall take place within the site until the applicant, or their agents or successors in title has secured the implementation of a programme of archaeological work in accordance with a written scheme of investigation which has been submitted by the applicant and approved in writing by the local planning authority.
The reason for the condition is :-
In order to record and safeguard any important archaeological remains that may be present on the site. |
| 4. | No development shall take place until the following items have been submitted to and agreed in writing with the local planning authority in conjunction with Environmental Health Officers:-
1) Installation of sub-floor ventilation;
2) Sealing of cavities and services entry points
3) Installation of a gas detection system.
The reason for the condition is :-
To ensure the safety of all users of the building. |
| 5. | Prior to the first occupation of the unit hereby permitted the on-site car and cycle parking area shall be laid out, demarcated, levelled, surfaced and drained and retained thereafter available for that specific use.
The reason for the condition is :-
To ensure the provision of adequate on-site parking and turning facilities for the development.
|
| 6. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the provisions of the great Yarmouth Borough Wide Local Plan and, in particular, policies EMP8 and BNV18. |
| 7. | THE APPLICANT'S ATTENTION IS DRAWN TO THE FOLLWOING NOTES FROM ENVIRONMENTAL HEALTH OFFICERS AND THE ENVIRONMENT AGENCY:-
The applicant is requested to to consider any measures that are necessary to safeguard against any potential hazard rising from landfill gas in this area. The applicant is also advised to contact the Building Control Officer and the Environmental Health Officer to ascertain any other special measures that may be necessary.
POLLUTION CONTROL:
The pollution of ground water and/or surface water is an offence under the Water Resources Act 1991. The applicant should therefore consider the following, as a minimum, to ensure that controlled waters are not polluted.
1) Prior to being discharged into any watercourse, surface water sewer or soakaway system, all surface water drainage from parking areas and hard standings susceptible to oil contamination shall be passed through an oil separator and constructed to have a capacity and details compatible with the site being drained. Roof water shall not pass through the interceptor. All washdown and disinfectant waters shall be discharged to the foul sewer. Any detergents entering oil separators may render them ineffective.
2) All cleaning and washing operations should be carried out in designated areas isolated from the surface water system and draining to the foul sewer (with the approval of the sewerage undertaker). The area should be clearly marked and a kerb surround is recommended.
3) Vehicles loading or unloading bays and storage areas involving chemicals, refuse or other polluting matter shall not be connected to the surface water drainage system.
4) No foul sewage or trade effluent, including cooling water containing chemical additiives, or vehicle washing water, including steam-cleaning effluent, shall be discharged to the surface water drainage system.
5) Only clean, uncontaminated surface water should be discharged to any soakaway, watercourse or surface water sewer.
6) Any facilities, above ground, for the storage of oils, fuels or chemicals shall be provided with adequate, durable secondary containment to prevent the escape of pollutants. The bunded area shall be designed, constructed and maintained in order that it can contain a capacity not less than 110% of the total volume of all tanks or drums contained therein. All filling points,vents, gauges and sight glasses should be bunded. Any tank overflow pipe outlets shall be directed into the bund. Associated pipework should be located above ground and protected from accidental damage. There shall be no gravity or automatic discharge arrangement for bund contents. Contaminated bund contents shall not be discharged to any watercourse, land or soakaway. The installation must, where relevant, comply with the Control of Pollution (Oil Storage) (England) Regulations 2001 and the Control of Pollution (silage, slurry and Agricultural Fuel Oil) Regulations 1991 and as amended 1997.
7) All drums and small containers used for oil and other chemicals shall be stored in bunded areas that do not drain to any watercourse, surface water sewer or soakaway.
8) Facilities should be provided to ensure that waste oil is stored and disposed of in a manner that will not lead to pollution. Site occupiers intending to purchase or install pollutant secondary containment (bunding) should ensure that the materials are not vulnerable to premature structural failure in the event of a fire in the vicinity. |