| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development hereby permitted shall be carried out in accordance with the planning application and plans (Drawing Nos. 555/1, 2, 3, 4, 5, 6) received by the Local Planning Authority on 3rd October 2008, unless otherwise agreed in writing by the Local Planning Authority.
The reason for the condition is :-
For the avoidance of doubt and in the interests of the satisfactory development of the site in accordance with the approved plans. |
| 3. | No work shall commence until the exact type and colour of the facing bricks and roof tiles, and the colour to be applied to the render, have been submitted to and approved by the Local Planning Authority.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of these materials have not been submitted. |
| 4. | Prior to the first occupation of the dwelling hereby permitted the proposed on-site car parking/ turning area shall be laid out, demarcated, levelled, surfaced and drained in accordance with the approved plan and retained thereafter available for that specific use.
The reason for the condition is :-
To ensure the provision of adequate on-site parking and turning facilities for the development.
|
| 5. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria for domestic additions set out in Policy HOU18 of the adopted Great Yarmouth Borough-Wide Local Plan, and is in accordance with Policy NNV2 of the adopted Great Yarmouth Borough-Wide Local Plan. |