Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The materials to be used in the external finishes of the development hereby permitted shall match those used in the existing building unless otherwise submitted to and agreed in writing by the local planning authority. The reason for the condition is :- To ensure the satisfactory appearance of the development.
3.The development hereby approved shall be constructed in accordance with the flood defence mitigation measures as submitted by letter dated 29th October 2008. The reason for the condition is :- To minimise the possibilities of flooding and to ensure the safety of those working on the site.
4.Prior to the first use of the development hereby permitted an additional fire door shall be provided on the Southeastern elevation (Elevation C Plan no: RS/2841/08/02). Reason for the Condition. To ensure the safe passage of users of the building in the event of a fire.
5.Prior to the first commencement of the use hereby approved an on-site parking area, comprising five additional car parking spaces shall be laid out, demarcated, levelled, surfaced and drained and retained thereafter available for that specific use. The reason for the condition is :- To ensure the provision of adequate on-site parking and turning facilities for the development.
6.REASON FOR APPROVAL OF THE APPLICATION :- The proposal meets the requirements of Policy EMP8 of the adopted Great Yarmouth Borough-Wide Local Plan.