Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.The substation hereby permitted shall be the version described on Drawing No. El 07-0101-1 as "ALTERNATIVE PITCH OF ROOF (IF REQUIRED)", i.e. that which has a common pitched roof with gable ends to the sides of the building. The reason for the condition is :- For the avoidance of doubt.
3.REASON FOR APPROVAL OF THE APPLICATION :- The proposed substation is intended as a replacement for an existing open compound site which is in poor condition.