| No. | Condition Text |
|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission.
The reason for the condition is :-
The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be carried out in accordance with the revised plan received by the Local Planning Authority on 24th June 2008.
The reason for the condition is :-
For the avoidance of doubt. |
| 3. | Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) Order 1995 (or any order re-voking and re-enacting that Order with or without modification), no dormer winows or other openings (other than those specifically granted by this permission) to the roofspace shall be provided and no alterations to the windows in the dormer over the main entrance shall be carried out unless otherwise specified in writing by the Local Planning Authority.
The reason for the condition is :-
In the interests of the residential amenities of the occupiers of adjacent residential properties. |
| 4. | No development shall take placewithin the site until the applicant, or their agents or successors in title, has secured the implimentation of a programme of archaeological mitigratory work in accordance with a written scheme of investigation which has been submitted to and approved in writing by the Local Planning Authority, which programme shall (for the avoidance of doubt) include (if considered by the Local Planning Authority to be necessary) post excavation assess ment, analysis, archiving and publication of results to the satisfaction of the Local planning Authority.
The reason for the condition is :-
To enable investigation and recording of the site of archaeological interest to take place during the period of building works and to ensure the foundations do not adversely effect the archaeological deposits. |
| 5. | No work shall commence until the exact type and colour of the roof tiles have been submitted to and approved by the Local Planning Authority.
The reason for the condition is :-
In the interests of the visual amenities of the area as precise details of these materials have not been submitted. |
| 6. | The garage shall only be used for private domestic use in connection with adjoining dwelling.
The reason for this condition is:-
In the interests of the residential amenities of the occupiers of adjacent property. |
| 7. | Prior to the property first being brought into use the roof light on the southern elevation to bedroom one shall be obscure glaze in accordance with details to be submitted to and agreed in writing with the Local Planning Authority and thereafter maintained in the approved condition.
The reason for the condition is :-
In the interests of the amenities of the occupiers of the adjacent residential properties. |
| 8. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria for domestic additions set out in Policy HOU18 of the adopted Great Yarmouth Borough-wide Local Plan. |