| No. | Condition Text |
|---|
| 1. | This permission expires on 3rd June 2013 and unless on or before this date application has been made for an extension to the period of permission and such application is approved by the Local Planning Authority, the portakabin shall be removed from the site.
The reason for the condition is:-
In order to retain control over the building which is constructed of short lived materials and in the interests of the visual amenities of the locality. |
| 2. | The development shall be constructed with a minimum finished floor level of at least l.92m AOD as stated in paragraph 5.1 of the Flood Risk Assessment.
The reason for the condition is :-
To ensure that the development remains dry in the event of flooding for the adequate protection of the occupants.
|
| 3. | Prior to the occupation of this development, a flood response plan shall be submitted to, and agreed in writing with, the Local Planning Authority. Once agreed this shall form part of the Health and Safety File for the building, under the Construction, Design and Management (CDM) Regulations. The response plan shall include a Flood Response Statement and Business Flood Plan which should be passed onto any subsequent owners of the building.
The reason for the condition is :-
To ensure that the owners and visitors of the site are aware that the land is at risk of flooding and of the procedures for evacuation. |
| 4. | The current and any subsequent owners, are responsible for erecting suitable permanent warning notices detailing the nature of the flood risk and the flood plan for this site. Furthermore, a fixed sign shall be displayed permanently at each entrance to the site giving this information. All signs shall be kept legible, clear of obstruction and up-to-date if flood risk information changes.
The reason for the condition is :-
To ensure that the owners and visitors of the site are aware that the land is at risk of flooding. |
| 5. | Prior to commencement of development, a means for securely anchoring the building shall be submitted to and approved by the Local Planning Authority.
The reason for the condition is :-
To prevent the building from becoming buoyant during a tidal flood event. |
| 6. | REASON FOR APPROVAL OF THE APPLICATION :-
The proposal meets the criteria of Policy EMP15 of the Great Yarmouth Borough-Wide Local Plan. |