Great Yarmouth Borough Council Portal
No.Condition Text
1.The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004.
2.No work shall commence until the exact type and colour of the facing bricks and roof tiles have been submitted to and approved by the Local Planning Authority. The reason for the condition is :- In the interests of the visual amenities of the area as precise details of these materials have not been submitted.
3.The development shall be constructed with a minimum finished floor level that is no lower than existing. The reason for the condition is :- To minimise the damage to the development in the event of flooding.
4.Prior to the commencement of any development, a flood response plan shall be submitted to and agreed in writing with the Local Planning Authority. This flood response plan shall be made available to future occupants of the dwelling by means of a fixed notice within the building prior to habitation. The reason for the condition is :- To ensure that occupants of the development are aware that the site is at risk of flooding.
5.Prior to the commencement of development, a scheme for the provision and implementation of flood proofing measures shall be submitted to and agreed in writing with the Local Planning Authority. The scheme shall be carried out in its entirety before the development is first occupied and should be constructed and completed in accordance with the approved plans and in line with the CLG publication 'Flood Resilient Construction - Improving the flood performance of new buildings'. The reason for the condition is :- To minimise the damage to the development in the event of flooding and enable a faster recovery once floodwaters have subsided as is set out in paragraph 5.41 of the PPS25 Practice Guide.
6.No part of the proposed structure shall overhang or encroach upon the highway boundary and no gate, if installed, shall open outwards over the public footway. The reason for the condition is :- To prevent obstruction of the public highway in the interests of highway safety.
7.REASON FOR APPROVAL OF THE APPLICATION :- The proposals meet the criteria for new housing development set out in Policies HOU7 and HOU15 of the adopted Great Yarmouth Borough-wide Local Plan