| No. | Condition Text |
|---|---|
| 1. | The development must be begun not later than three years beginning with the date of this permission. The reason for the condition is :- The time limit condition is imposed in order to comply with the requirements of Section 91 of the Town and Country Planning Act 1990 as amended by Section 51 of the Planning and Compulsory Purchase Act 2004. |
| 2. | The development shall be constructed with a minimum finished floor level of 1.05m AOD for the single storey studios. A minimum finished floor that is no lower than the existing shall be used for the restaurant extension. The reason for the condition is :- To ensure that the development remains dry in the event of flooding for the adequate protection of the occupants. |
| 3. | Prior to the commencement of development, a scheme for the provision and implementation of flood proofing measures shall be submitted to, and agreed in writing with the Local Planning Authority. The scheme shall be carried out in its entirety before the development is first occupied and constructed and completed in accordance with the approved plans and in line with the CLG publication 'Flood Resilient Construction - Improving the flood performance of new buildings'. The reason for the condition is :- To minimise the damage to the development in the event of flooding and enable a faster recovery once floodwaters have subsided as is set out in paragraph 5.41 of the PPS25 Practice Guide. |
| 4. | REASON FOR APPROVAL OF THE APPLICATION :- In the interests of improving facilities at the College. |